What was awarded, what it supports, and what still needs checking.

ABB doesn’t say a grant is at risk without a grant condition or official source. When a vote result isn’t posted, we say so.

Status: planning underway

Banning Armory Community Resilience Center

Official project page
Funder
California Strategic Growth Council
Published amount
The City describes a $1 million planning grant
Purpose
Plan the Art Welch Community Center as a community, climate-resilience, and emergency-operations facility
Published target
Plan completion in spring 2027
Department
Parks and Recreation
Not yet located
Full agreement, spending, balance, reimbursement schedule, City match, and responsible staff role
Status: amendment placed before Council

Encampment Resolution Funding, Round 2

Official agenda
Funder
California Department of Housing and Community Development
Award amount
$980,461
Original term
August 7, 2023 through March 31, 2027
Proposed amendment
Extend through April 30, 2028; no award increase or added City match
Reported results
187 clients served and 41 discharged to permanent housing through July 9, 2026
Estimated programmable balance
About $114,001.41 after accounting updates: $34,001.41 for interim shelter and $80,000 for rapid rehousing

Decision status The July 14 agenda recommended approving Resolution 2026-100. ABB didn’t locate posted minutes confirming the final result as of August 25.

Status: agreement before Council on August 25

Two-Way Cycle Track Safety Pilot

Official staff report
Funder
Southern California Association of Governments
Award amount
$895,000
City match
No City cash match required
Design and outreach
$275,000 administered by SCAG
Reimbursable installation
Up to $620,000; a future appropriation will be needed when the contract is awarded
Expected duration
Two years, with a temporary demonstration for about six months

Decision status The staff report recommended approving Resolution 2026-121. The meeting was in progress when ABB checked the record, so the outcome isn’t shown as final yet.

Official sources verified August 25, 2026.

Back to the public record guide

Grants & Outside Funding

See what’s confirmed, what’s missing, and who must follow through.

First verified entry

Separate the award from the money spent.

The tracker starts with one confirmed award. ABB won’t say money is at risk without a grant condition or official source.

Status: planning underway

Banning Armory Community Resilience Center

Official project page
Funder
California Strategic Growth Council
Published amount
The City describes a $1 million planning grant
Purpose
Plan the Art Welch Community Center as a community, climate resilience, and emergency operations facility
Published target
Plan completion in spring 2027
Department
Parks and Recreation
Not yet located
Full agreement, amount spent, balance, reimbursement dates, City match, and responsible staff role

Unresolved question Who will submit reimbursements and compliance reports if department staffing changes? ABB has not confirmed that the award is at risk.

Data needed for a complete tracker

  • Grant name, funder, amount, and purpose
  • Dates, City match, deadlines, and reports
  • Responsible role, amount spent, and remaining balance
  • Applications submitted, awarded, declined, or expired

Help keep this record accurate.

Send the source, page number, and a short explanation. ABB will publish corrections when a material fact changes.

Submit a recordSend a correctionAsk a question